Road Projects

137TH AVENUE ROADWAY IMPROVEMENTS

from Parrish Ave to eastern CSX RxR Tracks

Projected Project Start/End:  May 3rd to June 21st 2023   

Scope of Work:  Concrete curb and sidewalk ramp replacement at Doffin St & Highland St intersections, asphalt patching and resurfacing, pavement striping, landscaping restoration

Traffic:  The project work zone will be open to local traffic only during daytime construction hours 7am – 7pm, short term closures at times are possible.  Please use an alternate route if possible and drive slow with caution.

5/16/2023 Note from our Project Manager: 137th Avenue roadway project to take place tomorrow through Friday (17th-19th) weather pending. 137th Avenue will be closed (from Parrish to CSX RxR Tracks) during working hours (7am – 7pm). There will be a signed detour set up for traveling public to use Lauerman, 141st, and Parrish to get around. Winding Creek folks will have to use Parrish for access. Residents on 137th are to park cars that they may need access to during working hours in Winding Creek. The road will open back up for traffic after each working period and will only have a 2” bump at the ends between each day (bump signs will be in place).

Road Project Map

ASPHALT ROADWAY CRACK SEALING PROJECT

W. 133rd Ave, W 141st Ave, Parrish Ave

 

Projected Project Start/End:  May 3rd to June 21st 2023   

Scope of Work:  Concrete curb and sidewalk ramp replacement at Doffin St & Highland St intersections, asphalt patching and resurfacing, pavement striping, landscaping restoration.

Traffic:  The project work zones will be open to traffic but flagged throughout the active work zones during daytime construction hours 7am – 7pm.  Please drive slowly and with caution.

2023 Crack Sealing Project Map

2023-1 CCMG PROJECT

SHADES SUBDIVISION PHASE 1A STORMWATER & ROADWAY IMPROVEMENTS PROJECT

AFFECTED ROADWAYS:

                    • 141ST AVE (CLOSED BETWEEN HOBART ST AND WHEELER ST WITH DETOUR POSTED VIA 133RD AVE)
                    • WHEELER STREET (LOCAL TRAFFIC & DELIVERIES ONLY)
                    • BERKLEY STREET (LOCAL TRAFFIC & DELIVERIES ONLY)

*CONSTRUCTION WILL BE STARTING SEPTBEMBER 21, 2023 AND WILL CONCLUDE IN LATE NOVEMBER 2023

Shades Road Project Vicinity Map141st Closure PhotoShades Project Detour Map

The entire project is a two-phase project that will take place in the fall of 2023 and spring of 2024 to include:
W. 141st Avenue (from Hobart St to Corporate Limit)
Wheeler Street (from W. 141st Ave to Dead End)
Sherman Street (from W. 141st Ave to Dead End)
Berkley Street (from W. 141st Ave to Dead End)
Edison Street (from W. 141st Ave to Dead End/W. 140th Ave)
Rocklin Street (from W. 141st Ave to Dead End)
Marys Lane (from Edison St to Rocklin St)
Those roads that are not paved this fall will commence in the spring and a new schedule will be posted when it does.